By the end of August, the Village of Egg Harbor will complete land purchases needed for a right of way. That allows for construction on County Road G to begin in the fall. Engineer Mike Simon says that contingent on approval from the Board of Trustees this week, utility work should be started in a couple months.
It consists of burying storm sewers, along with installing gutters and lighting to be completed this fall. Roadwork is set for spring. The fall detour to reach downtown businesses is Dock Road. A gate that closes the street for marina traffic typically reopens in September.