You will be able to travel through a couple of Algoma’s main streets without taking any detours in the next few weeks. City Administrator Matt Murphy says all the infrastructure for sewer and water on Division Street is in the ground. The curb and sidewalk work is to be completed this week, with the binder coating of the pavement being done next week.
Murphy notes that the plan is to temporarily have Jefferson Street reopened to traffic Friday with a gravel base until it is ready to be blacktopped. The permanent paving and reopening of the streets are scheduled for completion by the second week of November.