Thanks to some good luck on the construction front, you will see a greenhouse grow at Southern Door School District. Miron Construction shared an update with the Southern Door School Board during its meeting on Monday, pointing out that some contingency funds are available for the district. The contingency funds were put aside just in case there were unexpected costs like price increases, design modifications, and weather-induced delays. Since Miron Construction did not have to dip into those funds, they will be able to build the greenhouse and complete it by the end of this summer. While the contingency funds will cover the building, interim Superintendent Tony Klaubauf says the district is looking at ways to pay for what it needs to fill it.
Phase two of the referendum projects, which includes the multi-purpose athletic facility, is on track to be finished before next school year. Klaubauf says they are working on some of the details of the new facility, such as naming rights, the location of its fitness center, and public access.