The west side redevelopment in Sturgeon Bay of a promenade is progressing with hopes of starting work in the fall. At last week’s Sturgeon Bay Common Council meeting, Community Development Director Marty Olejniczak shared details of the upcoming addition to the city’s waterfront. He notes the status progression of the design plans from 30 percent to 60 percent for the promenade after public input.
Representatives from Cedar Corporation and SRF Consulting group presented updated plans for the new promenade that will be built between the two bridges on the west side waterfront. Mayor David Ward noted in the meeting that hopes are for the entire project to be completed by early May of 2021.