You could be traveling down one of Algoma’s busier main streets sooner this summer than expected. Public Works Director Matt Murphy says a one-week head start on the project and cooperative weather have led to the Third Street construction in Algoma to be well ahead of schedule. He says Phase one of the street construction, from Clark Street to Steele Street, should be done this week.
Phase two of the $780,000 project will start Monday and go north to Navarino Street. Murphy asks that drivers avoid the construction area until the work is completed in early August.