You will be able to travel south of Sturgeon Bay on Highway 42/57 without any orange barrels and one-lane closures after next month. The Wisconsin Department of Transportation is completing the resurfacing of the last stretch of the roadway at the Highway 57 junction in the town of Nasewaupee. DOT Project Communication Manager Mark Kantola says the whole project should wrap up in late September as crews just finished diamond grinding northbound in the inside lane from County MM to Stagg Road this past week. The $7.5 million project began in late March and also improved intersections at Ashland and Neenah Avenue, County Road U/ Circle Ridge Road, and the Green Bay northbound ramp off Highway 42 in Sturgeon Bay.