The City of Algoma has everything on target to have the only major street construction project done in the next few weeks.
Algoma City Administrator Matt Murphy says the infrastructure construction of water, sewer, and storm sewer on Division Street is done, and crews are now completing work on three blocks of Frank Avenue. He says the infrastructure work should be done next Wednesday.
Murphy expects the road-building crew to finish the project by the middle of June when the paving and concrete work is expected to begin. He notes that Jefferson Street, Highway 54, will be entirely open for through-traffic over the Memorial Day weekend. Paving operations may temporarily close Jefferson Street in early July when the project is being completed.