Sister Bay’s waterfront is changing again, as the Marina office, restrooms and boater space undergo a complete remodel. Demolition of the Marina building began this week, with parts and pieces of the building being donated to various non-profit organizations around Door County.
Village of Sister Bay Marina Manager David Lienau talked with Door County Daily News on Thursday about what’s coming for the Marina building.
By November 30, the building will be completely demolished, construction started on the new structure right away, with a timeline calling for building occupation by next May 12, and scheduled completion by the end of August 2027.
The Sister Bay Marina will close down as usual for the winter - the public and boater restrooms already drained, as they’re not winterized - which will allow construction work to proceed without interruption, except for weather.
The new building will be 4,269 square feet in two stories: 2,582 sq. ft. on the first floor and 1,687 sq. ft. on the second floor, with offices and restrooms remaining on the main floor. On the second floor, there will be meeting rooms - which will be available for public rental, and a boaters lounge upstairs. The Marina will retain two sets of restrooms, giving both upgrades: boaters restrooms will include showers; the public restrooms will again be divided into two, with the addition of unisex bathroom that will be heated and open year-round - no more port-a-potties.
All in, the project cost is $2.4 million, Lienau said, “But there’s not a single taxpayer dollar that goes into Marina operations, all Marina funds are self-generated,” he said.
Funding for the building project is separated into two: the marina building as an enterprise-fund expense (privately funded by Marina revenue), and the standalone public restrooms as a general-fund expense from the Village’s budget.
The contractor for the project is Elite Builds, Inc. The last time the Sister Bay Marina was upgraded was in 2012, expanding the marina to 100 slips. No changes are being made to the 150 boat slips at this time.
A new sewer outfall pipe will be dug and installed as part of this project, moving it slightly north, and out from under the current Marina building. This is the outfall pipe for the entire Village’s treated sewer outfall, Lienau explained, which does run 250 feet out from the shoreline into the Bay.
The outfall pipe replacement involves coordination with the Village Wastewater treatment plant: the plant will have to keep one of three tanks unfrozen throughout the winter. When it comes time in March for the outfall pipe to switch from the old to the new, the treatment plant will have to store liquid. Lienau said the plant has the capacity to store for two days, so the Marina construction crews will have to move quickly.
The design echoes Horseshoe Bay Resort buildings, with a bit from the Sister Bay Beach Condos that sit across the highway from the Marina. What will catch people’s eye the most will be the copper roof, which Lienau said was just part of the bid by the contractor to get the project.