As work on WIS 42 begins to conclude, other road construction projects will ramp up over the next several weeks.
SISTER BAY
Beginning June 24th, the Village of Sister Bay will paint its crosswalks. The work is expected to be completed in the early morning hours.
BRUSSELS
The Door County Highway Department will begin a resurfacing project on CTH DK from Stone Road to CTH H at the beginning of next month. Crews will begin sawing of asphalt and concrete driveways on July 1st, with the removal of materials, road pulverization, and grading and compaction scheduled to start the week of July 8, 2024. After that, the placement of two lifts of asphalt is scheduled to begin on July 15th, with road shouldering and centerline markings completing the project. The work is expected to be done on August 8th.
As always, motorists are expected to drive carefully through the roadwork zones to guarantee not just their safety, but the lies of the worker.