Your travels on Highway 57 around Sevastopol will need to continue on a detoured route as the Wisconsin Department of Transportation continues to work on improvements to drainage structures. Crews are replacing a concrete box culvert and installing a new box girder bridge at Geisel Creek.
This week, construction crews at Geisel Creek will pour the bridge deck, finish the removal of the temporary diversion channel, and begin grading activities of the roadway and roadway embankment. Crews at Lily Bay Creek will begin structure backfill and removal of the temporary diversion channel.
The work is expected to be finished by the end of November. Areas around the closures will allow local traffic, but crossovers where the work is being done will not be allowed.
The project is part of a $3.3 million improvement plan contracted for Door County and will include work next spring and fall in Jacksonport at Logan Creek and Hibbard Creek.